DPW-23154- LCS Sam Glenn Complex Replace Server Room AC

Replace Server Room AC

Status

Accepting Bids

Prebid Date9/12/24 2:00pm

Bid Date9/26/24 2:00pm

Company & Contacts

Idaho Division of Public Works
Barry J. Miller  
208-332-1900

Location

Lewiston, Idaho

A description of the work of this project can be summarized to include the following: replacing an existing

computer room air conditioner (CRAC) that cools the college’s primary server room. In order to improve

the resiliency of the server room’s cooling system, two new CRACs will replace a single existing CRAC.

These two new CRACs will be complete with outdoor condensers sized for 120 deg F ambient conditions

and each will be sized to carry the full load of the server room. Modifications to the electrical system will

eliminate single points of failure by creating redundant electric supply (generator power and building

power) to both the CRACs and the individual servers equipped with dual power supplies.

Estimated Cost: $350,000